Orthophoto Insights: The orthophoto showcases key developments at the Riverside Homes site, with clear visibility of foundation work for several structures. The alignment of the built foundations is precise, indicating strong adherence to construction plans. Notable progress includes the installation of framing structures for the eastern section and concrete slab pouring.
DSM (Digital Surface Model): Elevation mapping reveals minimal deviations in elevation across the site. The highest point of elevation is 4.92 ft (center) and the lowest point is 2.21 ft (southeast). The relatively level grading ensures minimal runoff and a stable foundation. Site grading appears to be mostly completed, with small variations that may need to be addressed for final grading.
Ground Sampling Distance (GSD): 0.48 inches/pixel
Horizontal Accuracy (CE90): 0.55 ft
Vertical Accuracy (LE90): 0.35 ft
GPS Errors: None reported
Foundation and Framing:
The project has seen significant advancements since the last site visit. Most notably, the foundations for six units have been completed, with visible progress on framing in the central and western parts of the site.
Foundations for the southwestern blocks are fully formed and concrete cured.
Framing work has commenced, focusing on the central structure, where the skeletons of the buildings are beginning to take shape.
Site Layout and Organization:
Site organization has seen improvements with better material staging and clear pathways for construction vehicles. Notable improvements include the addition of new supply containers along the northern perimeter, and excavation work near the northwestern quadrant has progressed smoothly, with minimal disruptions to the overall construction timeline.
Visual Progress Comparison
Comparing this week’s orthophoto to previous captures, there is a clear progression in framing structures and foundational work. The site appears to be on schedule with foundations nearing completion and vertical construction well underway. No major structural delays are apparent based on the available visual evidence.
Stakeholder-Specific Notes
Cargill Employees:
As a key investor in this project, Cargill employees will be pleased to see the steady progression of Riverside Homes. With foundations now completed and framing actively occurring, the project remains on track to meet Q4 deadlines for completing the first phase of housing. Continued monitoring will ensure any delays or issues are flagged early, maintaining confidence in project timelines.
Real Estate Agents and Investors:
For real estate stakeholders, this progress marks an exciting phase as the first structures start to take shape. Once the framing is completed, the site will likely attract more potential buyers as they can better visualize the final product. Investors should feel reassured by the speed and organization at this stage, which sets the stage for a strong construction finish.
GSD: 0.48 in/pixel
Horizontal Accuracy (CE90): 0.55 ft
Vertical Accuracy (LE90): 0.35 ft
Processing Time: 1 hour 12 minutes
Images Captured: 284 JPG & DNG
Orthophoto and DSM: High-resolution images are available for stakeholders via the client web portal at www.303-drones.net.
Video: Hyper Lapse and Orbit
As construction continues, the next critical phase will involve completing the framing across all building units and preparing for roofing installations. The site appears well-organized for this progression. We anticipate further advancements in the coming weeks, with a focus on interior framing and electrical/plumbing groundwork. Expect the next report to include updates on roof truss installations, which are planned for early October.
For additional details or inquiries about the Riverside Homes project, contact Drone Pilot Edward Ryder at www.303-drones.net.
Ready to elevate your project with cutting-edge drone technology? At 303-Drones, we specialize in delivering detailed site monitoring, progress tracking, and aerial imaging services tailored to meet the needs of construction stakeholders, real estate professionals, and developers. From high-resolution orthophotos to precise elevation data, we provide insights that help you make informed decisions every step of the way. Contact us today to discuss how Drone Pilot Edward Ryder and our DJI Mavic 2 Zoom can support your project, ensuring accuracy and efficiency from start to finish.